Service Area

Municipal

Project Size

18 acres

Project Length

16 weeks

Warranty

1 year (material + workmanship)

Contract Type

GMP

Rivermill Transit Facility

From Raw Ground to Ready Pad

Summit Construction & Development was brought on by the county public works department to deliver the sitework package for the Rivermill Transit Facility in Hall County. The site presented a compressed schedule tied to a tenant delivery date. We phased the work to keep the schedule moving, self-performing utilities so the job stayed on one schedule with one point of accountability. The project was completed on schedule, turning the site over ready for building permit inspection.

Scope of work
  • Installed 900 LF of storm drainage plus 12 detention structures
  • Installed 2,350 LF of water main including fire service and hydrants
  • Completed with full OSHA compliance and zero recordables
Built to Comply

Public work runs on credibility. Every Summit project is staffed and documented to meet it.

  • Certified erosion and sediment control personnel on site
  • GDOT prequalified contractor
  • OSHA-compliant crews on site daily